Unofficial guidance to obtaining a building Permit for a new business in Dodgeville, WI



    TYPICAL PROCESS IN ORDER TO OBTAIN A BUILDING PERMIT FOR A NEW BUSINESS

    For detailed information, please contact the City of Dodgeville, Randy Edge, Assessor / Building Inspection. 608 935 9326

  • 1. OWNER MAKE INITIAL CONTACT WITH BUILDING INSPECTOR

  • 2. BUILDING INSPECTOR SETS UP MEETING BETWEEN BUILDING INSPECTOR, DIRECTOR OF PUBLIC WORKS AND OWNER OR OWNER'S REP.

    A. GO OVER ZONING CODE & ZONING MAP (SETBACKS, PARKING REGULATIONS STORM WATER REGULATION, ACCESS, ETC.)

    B. WATER & SEWER AVAILABILITY

  • 3. SET UP PLAN COMMISSION HEARING AND CITY COUNCIL MEETING IF NECESSARY

  • 4. DIRECT THEM TO STATE FOR PLAN REVIEW PROCESS

  • THE CITY PORTION OF THIS PROCESS CAN TAKE 6 TO 8 WEEKS.